Boondooma Dam

The spillway repairs project strengthened the existing spillway chute at Boondooma Dam. The scope included installing anchors in the existing spillway chute, concrete lining the spillway walls and earthworks to stabilise the right hand side of the spillway wall.
It also included:
  • Dewatering plunge pool average 8m in depth prior to works commencing, the removal and
  • relocation, in the dam and surrounding area, of all flora and fauna found
  • Filling of plunge pool to create access ramp with 40,000m3 of site won material.
  • Drill and blast approx. 55,000m3 of rock
  • Excavate and remove approx. 110,000m3 to stockpile
  • Drill and Install rock anchors (15,000m) ranging in size from 32mm dia to 75mm dia and
  • from 6m to 24m in length.
  • The FRP of approx. 5,500m3 of concrete to spillway chute floor and walls
  • FRP of concrete access road (2,850m2)
  • Associated drainage works including box culvert, concrete lined v-drains, rock drains
SHARE
LOCATION
Queensland
CLIENT
Sun Water
VALUE
A$14m
START
Nov 2016
END
Jna 2018
CAPABILITY
Water, Construction

You might also like...

Wetlands/irrigation/floodways  – Riverine Recovery Project (RRP)

Wetlands/irrigation/floodways – Riverine Recovery Project (RRP)

  • SECTOR: Water
  • LOCATION: Adelaide

The Riverine Recovery Project (RRP) forms part of the South Australian Riverland Floodplains Integrated Infrastructure Program (SARFIIP), a Commonwealth funded program to restore the health...

READ MORE
Wetlands/irrigation/floodways  – Katfish Reach Hydrological and Fish Passage Structures

Wetlands/irrigation/floodways – Katfish Reach Hydrological and Fish Passage Structures

  • SECTOR: Water
  • LOCATION: Berri, Riverland

The Katfish Reach Hydrological and Fish Passage Structures project was a significant project, part of a joint Federal and State government initiative designed to improve...

READ MORE
Water Supply –  Naracoorte Water Supply Upgrade

Water Supply – Naracoorte Water Supply Upgrade

  • SECTOR: Water
  • LOCATION: Naracoorte

This project included the design and construct of water supply network infrastructure that supplies 100% disinfected water to customers in the Naracoorte area, as part...

READ MORE
Water Supply  – Hackney Road and North East Road Trunk Water Main Upgrade (D&C)

Water Supply – Hackney Road and North East Road Trunk Water Main Upgrade (D&C)

  • SECTOR: Water
  • LOCATION: Adelaide

The Hackney Road project section involved 2.2km of pipe relining, underboring, and complete replacement of various sections of pipeline. The pipe alignment ran through the...

READ MORE
Water storage –  Werribee Aquifer Storage and Recovery Project

Water storage – Werribee Aquifer Storage and Recovery Project

  • SECTOR: Water
  • LOCATION: Adelaide

The first of its kind in Victoria, the scheme involved pumping treated water from Werribee Salt Reduction Plant through a series of underground pipe networks...

READ MORE