Heidelberg Track Duplication

Works are well under way at Heidelberg where the team have been tunnelling away at the new Darebin Street underpass. A special excavator called a Butor has been used, playfully nicknamed Boris by some of the tunnelling crew. Boris has made its way all the way from France and is being used for the first time in Australia. On average, it excavates approximately 40 cubic metres of rock daily, enough to fill a shipping container!

Meanwhile, another specialty machine, called an Akkerman, has been installing 36 metre long steel tubes on the south side of the Darebin Street underpass, which creates a canopy that stabilises the soil whilst the tunnelling takes place.

In exciting news, foundation works for the new Burgundy street rail bridge are making great progress, with the 41.3 metre long bridge deck to be lifted into place in early 2018. A new retaining wall is being constructed varying in size, from 2.5 to 9.3 metres high  on the north side of Burgundy Street. On the south side the concrete retaining wall has been completed. This wall will support the additional set of tracks that are being constructed as a part of the project.

The efficiency and determination of the crew is a positive sign as the 44 day construction blitz approaches.

Copy LinkEmailTwitterLinkedIn

You might also like...

Let’s talk about summer internships

Let’s talk about summer internships

Written by Nicola Wilson, General Manager People and Culture NZ,...

Read More
Fulton Hogan expands regional Victorian footprint with commencement of Loddon Mallee VRMC

Fulton Hogan expands regional Victorian footprint with commencement of Loddon Mallee VRMC

Fulton Hogan officially commenced operations under the Victorian Road Maintenance...

Read More
Water reform in New Zealand: What global experience tells us

Water reform in New Zealand: What global experience tells us

Written by Simon Drew, National Water Manager, Fulton Hogan.  ...

Read More