A Christmas present for Hamilton

20 December 2024:

Despite finding a series of unrecorded underground services, Waikato has completed the Borman Road connection almost three months ahead of its February 2025 deadline.

Project managed by Marco van Dam, it is part of Hamilton City Council’s development of the northern suburb of Rototuna. The project involved upgrading and extending Borman Road (by 600m), upgrading Horsham Downs Road and linking the two roads with a new intersection. There were also 3 waters upgrades and a new shared pathway. Almost the entire Waikato business was involved – the maintenance team even helping with letter drops!

The rapid growth of this formerly rural area meant residential and commercial stakeholder numbers climbed from 700 at the start to more than 1,000 by the end.

Pictured at the Blessing event on 9 December is, from left: Project Manager, Marco van Dam; HCC’s Dave Heatley and Shubham Asija; Regional Manager, Kerry Watkins; Stakeholder Manager, Sarah Carian; Contract Manager, Gordon Inglis; Site Engineer, Xyra Bernardo; Land Development Consultant, Aaron Fergusson; subcontractors Aaron West and Brad Laurence, Construction Labourer, Corban Calland.

Copy LinkEmailTwitterLinkedIn

You might also like...

Adelaide Airport soars to future-proof growth with Major Apron Expansion

Adelaide Airport soars to future-proof growth with Major Apron Expansion

Adelaide Airport has appointed Fulton Hogan as delivery partner for...

Read More
Fulton Hogan opens major new asphalt plant to strengthen Wellington’s infrastructure capability

Fulton Hogan opens major new asphalt plant to strengthen Wellington’s infrastructure capability

Fulton Hogan has officially opened its new Wellington Asphalt Plant...

Read More
Let’s talk about summer internships

Let’s talk about summer internships

Written by Nicola Wilson, General Manager People and Culture NZ,...

Read More