Fulton Hogan Delivers Christchurch Southern Motorway Stage 1 Ahead of Schedule
Fulton Hogan successfully completed the Christchurch Southern Motorway Stage 1 (CSM1), a transformative infrastructure project spanning 10.5 kilometres and connecting SH73 (Brougham Street Expressway) to SH1 (Main South Road). Delivered six months ahead of schedule, the project enhances connectivity across Christchurch and sets a benchmark for large-scale motorway construction in New Zealand.
Comprehensive Scope Across Three Zones
CSM1 was divided into three distinct zones, each with its own set of challenges and achievements:
- Zone A: Upgrade of Halswell Junction Road, Springs Road roundabout, and installation of traffic signals at Shands Road. Included 2.5 km of roadworks and utility upgrades.
- Zone B: Construction of a new four-lane median-separated motorway (5 km) with underpasses and realigned local roads.
- Zone C: Upgrade of 3 km of motorway between Collins Street and Curletts Road interchange, maintaining access to A&P Showgrounds and Canterbury Sale Yards.
- Additional works included 230m of PE250 watermain installation under Curletts Road and over 175,000 m² of pavement construction.
Performance and Achievements
- Delivered six months ahead of schedule and within budget.
- Zero Harm achieved across all zones; no LTI or MTI incidents.
- Environmental excellence with daily, weekly, and monthly audits in collaboration with Environment Canterbury (ECan).
- 98% quality KPI achieved across all works.
- Extensive stakeholder engagement and proactive communication.
- Use of recycled materials (RCC, asphalt tailings) for subbase and embankments.
- Awarded Health & Safety Award by Canterbury NZCF.
Sustainability and Innovation
Fulton Hogan implemented sustainable practices throughout the project, including the use of recycled crushed concrete (RCC) and asphalt waste in embankments. These initiatives reduced the need for virgin materials and minimised carbon emissions from cartage.
Innovative construction methodologies and stakeholder-focused planning ensured minimal disruption to residents and businesses, reinforcing Fulton Hogan’s reputation for excellence in infrastructure delivery.
Canterbury,
CLIENTNew Zealand Transport Agency Waka Kotahi
START DATEMarch, 2010
END DATEDecember, 2012
CAPABILITYTransport,
You might also like...
 
                                Keeping Mackenzie Moving
- CAPABILITY: Maintenance,
- LOCATION: Canterbury,
The Mackenzie District’s vast and varied roading network is in safe hands, thanks to a dedicated team of contractors and local partners working under the...
READ MORE 
                                Midland Port: Delivering a Modern Freight Gateway for Canterbury
- CAPABILITY: Ports,
- LOCATION: Canterbury,
The successful completion of the Midland Port Container Terminal in Rolleston stands as a milestone in Canterbury’s freight and logistics sector. Delivered for Lyttelton Port...
READ MORE 
                                Fairton Freight Hub: Transforming Ashburton’s Freight Future
- CAPABILITY: Transport,
- LOCATION: Canterbury,
The completion of the Fairton Freight Hub marks a major milestone for Ashburton’s transport and logistics sector. For the Wareing Group and partners for Fairfield...
READ MORE