NCI Project Nears Completion With A Flourish
- CAPABILITY: Transport,
- LOCATION: Auckland,
One of the final touches on the five-year Northern Corridor Improvements (NCI) project has also proved to be one of the more dramatic. A 30 shift (six week) project was completed in just 10 shifts by using three paving crews – running a milling, membrane and paving operation in parallel – to prepare for and […]
READ MORE
Putting The Speed In Speed Tables
- CAPABILITY: Precast,
- LOCATION: Auckland,
Pre-casting is changing the game in speed table construction. This pre-cast speed table, installed for Auckland Transport in Kumeu by Fulton Hogan’s pre-cast team, Stevenson Concrete, Fulton Hogan Minor Construction and Coastline Markers, took a single overnight shift to install. This compares with the two weeks typically required for traditional in situ construction, thereby minimising […]
READ MORE