NCI Project Nears Completion With A Flourish

NCI Project Nears Completion With A Flourish

  • CAPABILITY: Transport
  • LOCATION: Auckland

One of the final touches on the five-year Northern Corridor Improvements (NCI) project has also proved to be one of the more dramatic. A 30 shift (six week) project was completed in just 10 shifts by using three paving crews – running a milling, membrane and paving operation in parallel – to prepare for and […]

READ MORE
Putting The Speed In Speed Tables

Putting The Speed In Speed Tables

  • CAPABILITY: Precast
  • LOCATION: Auckland

Pre-casting is changing the game in speed table construction.  This pre-cast speed table, installed for Auckland Transport in Kumeu by Fulton Hogan’s pre-cast team, Stevenson Concrete, Fulton Hogan Minor Construction and Coastline Markers, took a single overnight shift to install. This compares with the two weeks typically required for traditional in situ construction, thereby minimising […]